Intensive maintenance works have been carried out on the Dubai Metro network during the national disinfection drive.
Officials at Dubai's Roads and Transport Authority (RTA) took advantage of the lockdown period in April to complete the work at a much quicker rate than usual.
The additional hours helped them finish the bulk of the project well ahead of the initial schedule, with the completion rate hitting 180 per cent in certain sections.
The work mainly focused on rail tracks, tunnels and other periodic as well as essential maintenance activities.
.@rta_dubai carries intensive rail maintenance during national disinfection programhttps://t.co/btME5t4N9I pic.twitter.com/5CKG2a5ra9
— Dubai Media Office (@DXBMediaOffice) June 21, 2020

UAE condemns Israeli targeting of Lebanese army vehicle
H.H. Sheikha Latifa to lead UAE delegation on official visit to Sweden
Sharjah Police recover resident’s life savings after bag left in taxi
UAE President appoints Hamad Al Kaabi Director-General of UAE nuclear regulator
RTA to partially open Dubai Harbour Bridge Project in June