DEWA desalination plant 92% complete

Twitter/(DXBMediaOffice)

DEWA's Seawater Reverse Osmosis (SWRO) desalination plant is 92.4% complete.

According to the emirate's electricity and water authority, the facility has a production capacity of 40 million imperial gallons of water per day. 

The project is set to be completed in Q4 of 2021 to meet the increasing demand for water in the emirate. 

DEWA aims to increase its SWRO production capacity to 303 MIGD by 2030; reaching 42 per cent instead of its current share of 13 per cent.

According to the authority's strategy, desalinated water will be produced 100 per cent by a clean energy mix that uses both renewable energy and waste heat by 2030. This will allow Dubai to exceed global targets for using clean energy to desalinate water.

More from Business

Coming Up on Dubai Eye

  • Nights on Dubai Eye 103.8

    11:00pm - 6:00am

    Dubai Eye complements the conversation with the music you love from the eighties, nineties and newer.

  • The Business Breakfast

    6:00am - 10:00am

    The Business Breakfast is the day’s must listen for the UAE’s business leaders, and those who aspire to be.

BUSINESS BREAKFAST LATEST

On Dubai Eye

  • Flying Taxis

    It sounds like an episode of The Jetsons, but the sight of flying taxis whizzing around our cities could be much closer than you think.

  • Tough penalties for deliberate tax evasion

    The UAE has said that tougher penalties will come into force from 1st August for not keeping proper corporate tax records.